Client:

Kingston Building

Duration:

3 weeks

Project Overview:

Approximately 4400m2, an old printing factory has been converted into a state of the art new and used car dealership and workshop. Project managed by Kingston Building.

Completed works:
  • Diamond grinding and shot blasting to prepare the substrate.
  • Application of epoxy repair mortar to damaged sections of substrate.
  • Application of HYCHEM MOTOR TUFF, five-layer high build epoxy topping system to the workshop floor area, approx. 1500m2.
  • Line marking to the workshop area.
  • Application of HYCHEM HARDENSEAL, penetrative sealer to the internal car parking areas, approx. 2900m2.
  • Removal and replacement of the existing expansion joints.